Location: St James's Square, London |
|
Our Role: Cost Management |
Full refurbishment of listed offices totalling circa
115,000 sq ft in a prime London location to provide a speculative Cat A development of the highest quality.
Works included the replacement of an existing mechanical VAV system to a 4 pipe fan coil installation, major building alterations and a structural glazed roof to the atrium.
The Client's key drivers were programme and quality. The overall project duration was 18 months with a 13 month period on site, the procurement challenges were managed with the design team by creating a procurement strategy that allowed the client a blend of cost certainty and speed of delivery. |